1.0 OBJECTIVE
To establish a standard operating procedure for startup and stop of Purified Water System.
2.0 SCOPE
This SOP is applicable for the Building Automation Systems of OSD Units of (Company Name).
3.0 RESPONSIBILITY
3.1 Operator shall be Responsible to follow the procedure strictly.
3.2 Supervisor shall be responsible to ensure that the SOP is followed properly.
4.0 ACCOUNTABILITY
4.1 Head of Engineering.
5.0 PRECAUTIONS
5.1 Concerned personnel should be trained on the SOP.
5.2 Ensure that power supply back up from UPS is available for the SCADA and PLC of Water System
5.3 Ensure that cable connections at the hub between the PLC and SCADA are properly secured.
5.4 Ensure that the printer is connected with the SCADA and is functioning properly.
6.0 PROCEDURE
6.1 Startup
6.1.1 Switch ON the PC of SCADA System
6.1.2 Click on “RSView32” on main screen
6.1.3 Click on “Continue”
6.1.4 Main screen of of the Plant Graphic is viewed
6.1.5 Main screen of of the Plant Graphic is viewed
6.1.6 Select required Option from the Menu
6.2 Shutdown
6.2.1 Main Screen of Plant Graphic
6.2.2 Running Parameter
6.2.3 Overview menu
6.2.4 Main menu
6.2.5 Exit Menu
6.2.6 Click on “Exit”
6.2.7 Click “ yes” to close RSView32