SOP for Challenge test of Bas System

Objective: To establish a standard operating procedure for challenge test of BAS system.

Scope: This SOP is applicable for the Building Automation Systems of OSD and MDI Units of (Company Name).

Responsibility
1 Operator shall be Responsible to follow the procedure strictly.
2 Supervisor shall be responsible to ensure that the SOP is followed properly.

Precautions
1 Concerned personnel should be trained on the SOP.
2 Ensure that power supply back up from UPS is available for the OWS and NCU (Network Control Unit).
3 Ensure that cable connections at the hub between the NCU and OWS are properly secured.
4 Ensure that the printer is connected with the OWS and is functioning properly.

Procedure
1 Switch ON the BAS system
2 Start Individual AHU step by step
3 Check the command execution of AHU given from BAS system according to Appendix-I from BAS system and AHU simultaneously
4 Create manual blockage in the filter and check alarms in the BAS system