*** Inspection & dynamic testing of systems or major system components to support the qualification of an equipment/system conducted at client site.
*** Establishing documented evidence that during receipt of the items / equipment / system at site, conform with the standard laid in the protocol, purchase order and manufacturer specifications.
*** To ensure that the site of installation is ready.
Minimum acceptance criteria for SAT
The items of equipment and system shall comply with:
*** Major component verification as per FAT report and specifications
*** Packing Material list
*** Physical condition of major components or machine
*** Operation testing / verification shall be perform
*** Manufacturer’s machine identification code / identification number.
Minimum document require for SAT
*** User Manual
*** Maintenance manual
*** Process & utility diagram
*** Electrical Schematics
*** Spare parts list
*** FAT report & specifications
*** Design specifications & drawings
*** Safety Rules
*** Qualification documents (if specify)