Purpose: To lay down operating procedure for operation of Soft Water plant.
Scope: This procedure is applicable to ……………
Responsibility: Production Chemist
To supervise the activity
Equipment used: Softener (Indion NGS – 3B)
Operating procedure:
1. Check the cleaning ...
Purpose: To lay down operating procedure for regeneration of demineralized water plant.
Scope: This procedure is applicable for …………….
Responsibility: Production Chemist
To supervise the activity
EQUIPMENTS USED:
1. Portable Deioniser
a) For anions & cations (Model ...
Purpose: To lay down operating procedure for regeneration of soft water plant.
Scope: This procedure is applicable to ………………..
Responsibility: Production Chemist
To supervise the activity
Equipment used: Softener (Indion NGS – 3B)
Regeneration procedure:
Brine ...
Objective: To establish a standard procedure for operating the Air-cooled Reciprocating chiller (Model-CR-18002A)
Scope: This procedure is applicable for the operation of Air -cooled reciprocating chiller, Model-CR 18002A of (Company Name).
Responsibility
1 Operator shall be responsible for following ...
Objective: To establish a standard maintenance procedure of Hoist
Scope: This SOP is applicable for Hoist of (Company Name).
Responsibility
1. Operator shall be responsible to follow the procedure strictly.
2. Supervisor shall be responsible to ensure that the SOP is followed properly.
Accountability: ...
Objective: To establish a standard preventive maintenance procedure for Electrical Lift.
Scope: This SOP is applicable for the Electrical Lifts installed at (Company Name).
Responsibility
1 Maintenance Engineer shall be responsible to follow the procedure strictly.
2 Supervisor shall be responsible ...
Objective: To establish a standard preventive maintenance procedure for Boiler.
Scope: This SOP is applicable for the preventive maintenance of Boilers (Cleaver Brookes, Model: CIW-700-200-150 & CIW-700-125-150) installed at the utility building of (Company Name).
Responsibility
1 Operator shall ...